Labor Productivity:
[
{Productivity} = \frac{{Work Completed (e.g., sqft, cubic yards)}} / {{Hours Worked}}
]
Measures how efficiently labor is used on the site.
Material Wastage Rate (%):
[
{Wastage Rate} = \frac{{Wasted Material Quantity}} / {{Total Material Used}} * 100
]
Tracks material efficiency to identify areas for cost savings.
Project Progress (%):
[
{Progress} = \frac{{Completed Work}} / {{Total Planned Work}} * 100
]
Monitors whether the project is on schedule.
Safety Incident Rate:
[
{Incident Rate} = \frac{{Number of Incidents} * 200,000}{{Total Hours Worked}}
]
Evaluates safety performance on the site.
Schedule Variance (SV):
[
{SV} = {Earned Value (EV)} - {Planned Value (PV)}
]
Measures whether the project is ahead or behind schedule.
Cost Variance (CV):
[
{CV} = {Earned Value (EV)} - {Actual Cost (AC)}
]
Indicates whether the project is over or under budget.
Scenario 1: Addressing Safety Violations
Scenario 2: Resolving Schedule Delays
Scenario 3: Managing Material Shortages
Scenario 4: Ensuring Quality Standards
Scenario 5: Coordinating with Subcontractors